This project is the renewal of Korepo Road water main and laterals to fix pressure-related leaks and improve reliability.
Current status |
Planning/ Design |
Start Date |
TBC |
End date |
June 2027 |
Access |
TBC |
Contractors |
TBC |
Cost |
TBC |
Contact: Email projects@tasman.govt.nz for further information, reference 1512.
Update August 2025
Iwa St, Mapua - Starting August
The water main on Iwa Street needs to be replaced due to its poor condition. There will be multiple stages to limit the effect to residents and businesses in the area. Stage 1 we will be installing the new 150mm PVC Watermain on the Western side.
Dates for the stage 1 works are expected to be 18th August – end of September 2025. During this time there will be Traffic Management in place, so please follow the signs and directions of staff. Stage 1 has a one-way system where you can only enter Iwa Street via Toru Street
Tahi St, Mapua - COMPLETE
The water main on Tahi Street needs to be replaced due to its poor condition. This will involve a new pipe under both sides of the road. Below is a diagram of stage one of the traffic management as we install the pipe from the carpark to Gossi Point along the eastern. We will send out the stage 2 traffic management closer to the time
Dates for the works are expected to be 16th June 2025 – 1st August 2025. During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
Hill Street works COMPLETE
The water main on Hill Street between #101 Queen St and 222 Hill St needs to be replaced due to its and age and poor condition.
Dates for the works are expected to be 3rd to 17th June.
During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
Update March 2025
Upper Queen/Hill Street COMPLETE
The water main on Queen Street between Hill St and #85 needs to be replaced due to its and age and condition. This also involves a pipe under the road and will close the Upper Queen Street section of road during works period. Works dates: 24th February 2025 – 4th April 2025. Once a separate project on Wensley Road works are complete (looking to be in April) we will then move on to Hill Street and have one way/stop go traffic management in place.
Update Jan 2025
Cautley Street - COMPLETE
The water main on Cautley Street between King Street and Giblin Street needs to be replaced due to its age and condition. Works have started and are expected for completion on 21st February 2025. From 4th February to 21st February, road access will be reinstated, with only a shoulder and footpath closed.
About the Project
This project is for a three year programme of reticulation renewals in the Tasman region. These renewals are an ongoing series of works across Tasman designed to renew failing water infrastructure.
First areas of work starting in Māpua and Richmond.
Current status |
Delivery |
Start Date |
Construction starting end of November as a rolling programme until mid 2027. |
End date |
June 2027 |
Access |
To be advised in each section. |
Contractors |
Ching Contracting |
Cost |
$1m for Year 1 |
Contact Us: Email Projects@tasman.govt.nz for further information reference 1534 Urban Water Reticulation Renewals